Premier is a gold-producer and respected exploration and development company with high-quality precious metal projects in proven, accessible and safe mining jurisdictions in Canada, the United States, and Mexico. Premier’s team is focused on creating a low-cost, mid-tier gold-producer from its two producing gold mines and two advanced-stage, multi-million ounce development projects.
2018 Fourth Quarter Highlights
- Production of 23,042 ounces of gold and 120,730 ounces of silver
- Cash costs1 of $619 per ounce of gold sold, a 28% reduction from Q3 2018
- AISC1 of $798 per ounce of gold sold, a 21% reduction from Q3 2018
- Revenue of $19.9 million
- Mine operating income of $6.1 million
- Production of 89,699 ounces of gold and 321,814 ounces of silver
- Sales of 87,036 ounces of gold at an average realized price1 of $1,264 per ounce
- Cash costs1 of $788 per ounce of gold sold
- AISC1 of $927 per ounce of gold sold
- Revenue of $113.9 million
- Mine operating income of $16.5 million
- Net loss of $20.4 million
“The Company’s strong financial position has provided us the opportunity to grow our future production through the advancement of our portfolio” stated Ewan Downie, President & CEO. “With two new mines under construction at South Arturo, and permitting underway at Cove and Hardrock, we expect to see significant increases in our future production profile”.
2018 Highlights – Three months and year ended December 31, 2018
A total of 23,042 ounces of gold and 120,730 ounces of silver were produced during Q4 2018 compared to 24,385 ounces of gold and 77,082 ounces of silver during Q4 2017. Co-product cash costs(1) during the period were $619 per ounce sold, representing a 28% or $239 per ounce cost reduction over Q3 2018. All-in sustaining costs (AISC)(1) of $798 per ounce of gold sold were lower by 21% or $210 per ounce, as compared to Q3 2018.
The Company reported total revenue of $19.9 million during the fourth quarter compared to $30.2 million during Q4 2017. The reduction in revenue and operating income, when compared to Q4 2017, is primarily the result of lower sales from South Arturo as a result of the planned processing of lower grade stockpiles following completion of the mining of the Phase 2 pit in 2017.
A total of 89,699 ounces of gold and 321,814 ounces of silver were produced during 2018 as compared to 139,658 ounces of gold and 357,901 ounces of silver during the prior year. Co-product cash costs in 2018 were $788 and AISC were $927 per ounce of gold sold.
The Company reported total revenue of $113.9 million in 2018 as compared to $200.3 million in the prior year. The reduction in revenue is the result of lower sales from both South Arturo and Mercedes Mines. A reduction at South Arturo was anticipated as the Company transitioned from Phase 2 production to El Nino underground and Phase 1 open pit development. Production and sales at Mercedes were lower than the prior year due to the requirement to redesign stopes in the Diluvio zone during the first half of 2018 following changes in geologic interpretations and resource modeling. This resulted in lower mined grades from the processing of development ore and less stope ore during this period.
In keeping with its longer-term objective of increased annual production over the next several years, the Company invested $22.2 million in exploration and pre-development initiatives during 2018 that, when factored with the reduction in mine operating income, contributed to a net loss of $20.4 million. Total capital spending during the year was $26.9 million including the construction of two new mining projects that have been initiated at South Arturo.
The Company closed the year with cash and cash equivalents of $43.9 million, having eliminated its long-term debt of $20 million in Q2 2018. The Company held inventory of 2,210 ounces of gold and 14,802 ounces of silver at year end.
Consolidated quarter and year end operating results are provided in Table 1 below.
The South Arturo Mine in Nevada, a joint venture operated by Barrick Gold Corporation (“Barrick”), continued to overperform during the quarter. Processing of stockpiled ore from the Phase 2 open pit during the fourth quarter has contributed to gold production that has exceeded full-year gold guidance with a total of 21,276 ounces delivered to Premier for the year.
Construction at two new mining centers at South Arturo has commenced with stripping of the Phase 1 open pit and development of the El Nino underground mine now underway.
Quarter and year to date operating results are provided in Table 2 below.
Capital expenditures of $3.6 million during the fourth quarter and $8.4 million for the year were mainly related to stripping for the Phase 1 open pit and underground development at El Nino.
Exploration activity in the fourth quarter and during 2018 focused on analysis of near pit and underground resource expansion drilling that occurred earlier in the year for Phases 1 and 3 and El Nino, respectively. A total of 6,279 meters was drilled in 2018.
Mercedes
Quarter and year to date operating results are provided in Table 3 below.
Mercedes production for Q4 2018 was 22,465 ounces of gold and 119,039 ounces of silver compared to 19,913 and 77,082 respectively during the prior year period. Co-product cash costs(1) during the period were $639 and AISC(1) were $808 per ounce of gold sold. Gold production from Mercedes in Q4 2018 improved over the prior year period due to higher mined grades upon transitioning to the new Rey de Oro and Lupita zones as well as consistent stope production from the Diluvio zone. Full year 2018 production at Mercedes was lower than the prior year due to the requirement to redesign stopes in the Diluvio zone during the first half of 2018 following changes in geologic interpretations and resource modeling. This resulted in lower mined grades from the processing of more development ore and less stope ore during this period. As a result, full year 2018 , co-product cash costs and AISC were higher than the prior year.
In addition to consistent production following the transition to new mining zones, initiatives to improve costs have been identified and are being tracked weekly by the site leadership team.
Exploration drilling continued during the fourth quarter with 1,972 meters completed for a total drilling of 40,721 meters for the year. An average of three drill rigs were on site for the quarter. Drilling continued to target the Diluvio, Marianas and Barrancas veins with a focus on replacing reserves, supporting mine production, testing extensions of the main mine trends and new geological targets.
Capital expenditures of $3.1 million were incurred during the fourth quarter for mine development in support of operations in new mining zones and increased production, including completion of the construction of a new tailings facility at the mine.
Cove and McCoy-Cove
A Preliminary Economic Assessment (“PEA”) was completed in the first half of 2018 on the McCoy-Cove project, including designs for underground exploration development and drilling, preliminary engineering, dewatering, and environmental baseline studies, and a life of mine plan. Underground exploration development is now expected to begin in the fourth quarter of 2019. Dewatering simulations, including a pump test of the proposed underground advanced exploration areas around the Helen Zone were completed during 2018. During the fourth quarter of 2018, spending focused on pre-development, including engineering and permitting to change the portal and power line to safer and more practical locations and changing the design of the waste rock stockpile to improve economics without compromising environmental risks. Well drilling, pump tests, and improving the groundwater model will be completed during the first half of 2019.
A McCoy-Cove “Earn-in” agreement was signed with Barrick Gold in December 2017 to explore the claims surrounding the Cove properties. During the fourth quarter, 1,431 meters were drilled with a total of 9,723 meters for the whole year concentrating on the top two priority target areas of Lakeside and Windy Point with a focus on vectoring towards the most favorable geologic controls. The drilling was split between the Windy point and Lakeside east extension areas, both with encouraging results.
Greenstone Gold Mines
At Greenstone, permitting related work continued on the property with the Environmental Assessment (“EA”) for the Hardrock Project (the “Project”) being approved on December 13, 2018 by the Honourable Catherine McKenna, Minister of Environment and Climate Change. The Provincial Ministry EA Review Report was issued for public comment on October 22, 2018 and approval is anticipated in 2019. Work on construction permit applications are well advanced and will be submitted for review once the federal EA and provincial EA’s are approved. Greenstone also, signed a Long-term Relationship Agreement with the Metis Nation of Ontario in December 2018 that provides for environmental, employment, training, business and contracting opportunities, along with a framework for regulatory permitting. A similar Agreement was signed with Long Lake #58 First Nation in June of 2018.
Hasaga
Goldbanks
A total of 1,762 meters was drilled during the fourth quarter for a total of 5,474 meters during 2018. Drilling during this period focused primarily on the Hawkeye target, located in the northwest portion of the property. In general, results for these shallow open-pit targets were disappointing and do not require additional follow-up.
All abbreviations used in this press release are available by following this link (click here).
Q4 and year end 2018 financial results and conference call details:
A conference call with senior management to discuss the financial results for the three months and year ended December 31, 2018 will be held at 10:00am EST, Thursday March 7, 2019.
Details for the conference call and webcast can be found below and will be accessible on the Company’s website.
Toll Free (North America): (+1) 888 390 0605
International: (+1) 416 764 8609
Conference ID: 10218835
Webcast Link: https://event.on24.com/wcc/r/1918438/329EB9095CAF51273BA2CB0C75E8F404
Conference Call Replay
The conference call replay will be available from 1:00pm EST on March 7, 2019 until 11:59pm EST on March 14, 2019.
Toll Free Replay Call (North America): (+1) 888 390 0541
International Replay Call: (+1) 416 764 8677
Passcode: 218835#
- A cautionary note regarding Non-IFRS financial metrics is included in the “Non-IFRS Measures” section of the Year ended 2018 Management Discussion and Analysis.
- Accounting policy change is discussed in Note 2(f) to the December 31, 2018 consolidated financial statements of the Company.
The Company has included certain terms and performance measures commonly used in the mining industry that are not defined under International Financial Reporting Standards (“IFRS”) within this document. These include: cash cost per ounce sold, all in sustaining cost (“AISC”) per ounce sold, earnings before interest, tax, depreciation and amortization (“EBITDA”), adjusted earnings before interest, tax, depreciation and amortization (“Adjusted EBITDA”), adjusted earnings / (loss) per share, free cash flow, capital expenditures (expansionary), capital expenditures (sustaining) and average realized price per ounce. Non-IFRS measures do not have any standardized meaning prescribed under IFRS, and therefore, they may not be comparable to similar measures employed by other companies. The data presented is intended to provide additional information and should not be considered in isolation or as a substitute for measures prepared in accordance with IFRS and should be read in conjunction with the Company’s consolidated financial statements. Readers should refer to the Company’s Management Discussion and Analysis under the heading “Non-IFRS Measures” for a more detailed discussion of how such measures are calculated.